Question: Councillor D. Smith – . “To ask the Chief Executive for an update on the works which have taken place on the Swords Waste Water Treatement plant in 2016 and to comment on whether there are any works planned for 2017?”
Reply: The main element of works yet to be completed is the testing and proving of the sludge digestion process. Preparations are underway to commence this process in the coming weeks and it is anticipated that this work will conclude in mid January 2017.