Question: Councillor D. Smith “To ask the Chief Executive for an update on taking in charge of street lighting in Boroimhe Alder, Beech and Hazel?”
Reply: The civil/electrical works necessary to transfer existing metered lighting supplies to unmetered have been completed and application has been made to ESB for 18 No. new connections. Based on current work schedules it could take from up to 8 weeks for these connections to be made live. Once verified by inspection, Fingal County Council will assume responsibility for the payment of the energy charges associated with the transferred lighting